Task Guide: Analyzing Watershed Hydrology Telemetry with PivotTables
Alpha status (14 October 2026): XiSheet is planned and its public installer is not verified. This page describes the checked GridCraft foundation; XiKey integration is still in progress. Alpha is free today.
Scenario Overview
In this guide, you will import a raw telemetry CSV from 18 mountain watershed gauging stations, split composite sensor strings using Text to Columns, scrub duplicate packet transmissions, build a PivotTable and Combo Chart comparing monthly rainfall against reservoir inflow, and run Goal Seek to determine the spillway release rate required to hold reservoir capacity at 82%.
Step 1: Import Telemetry CSV and Clean Sensor Strings
- Open the raw logger export (
watershed-telemetry-2026.csv) via File › Open. - Column
Acontains composite station tags formatted asBASIN04|STN-12|ELEV1840. Insert two empty columns to the right of ColumnA, selectA2:A4500, and click Data › Text to Columns:- Choose Delimited, set the delimiter character to
|(pipe), and split intoBasinID,StationCode, andElevationBand.
- Choose Delimited, set the delimiter character to
- Because satellite uplinks occasionally transmit duplicate hourly packets, select the full table (
Ctrl+Shift+8) and click Data › Remove Duplicates, checking onlyStationCodeandTimestampUTC.
Step 2: Build a Multi-Basin PivotTable with Prepared Source Columns
- With any cell in the cleaned telemetry table selected, choose Insert › PivotTable and place it on a new worksheet named
BasinSummary. - In the PivotTable Fields side panel, configure the layout:
- Rows:
BasinID, thenStationCode - Columns:
Month - Values:
Precipitation_mmset to Sum (formatted as#,##0.0 "mm")Streamflow_m3sset to Average (formatted as0.00 "m³/s")
- Rows:
- Before creating the PivotTable, add a source column for runoff volume: precipitation in millimetres × catchment area in square kilometres × 1000 × runoff coefficient. Summarize that column with Sum. This is an illustrative estimate, not a validated reservoir model.
- Right-click any basin row to collapse or expand individual gauging stations, and enable Grand Totals and Subtotals.
Step 3: Insert a Combo Chart (Columns + Line)
- Select the monthly summary range on
BasinSummaryand pressAlt+F1(or click Insert › Chart › Combo). - Configure the chart series in the Chart Inspector:
- Series 1 (
Total Precipitation mm): Clustered Column on the primary vertical axis. - Series 2 (
Mean Streamflow m³/s): Line with Markers plotted on the Secondary Axis.
- Series 1 (
- Set the chart title to
Upper Watershed Monthly Precipitation vs. Peak Streamflowand enable data labels on peak spring snowmelt months.
Step 4: Run Goal Seek on the Reservoir Storage Balance
- Switch to the
ReservoirBalancesheet, and enter initial storage, inflow, evaporation and maximum capacity in cubic metres into B2, B3, B4 and B5; put the release rate in cubic metres per second in B9. Cell B12 calculates storage percentage:=(B2+B3-B4-(B9*86400*30))/B5 - To find the exact continuous spillway discharge (
SpillwayRelease_m3sin cellB9) needed to keep end-of-month storage (B12) at exactly82.0%(0.82), open Data › What-If Analysis › Goal Seek:- Set cell:
B12 - To value:
0.82 - By changing cell:
B9
- Set cell:
- Click OK. Review the reported solution and confirm the balance independently; Goal Seek does not guarantee convergence for every model.